Do you want to make changes to your property? Then you may often need an environmental permit. You may perform a permit-check with Omgevingsloket Online.
Costs of a permit depend on the type of permit. Payment is also required if your permit application is denied. You may find an overview of the costs of environmetal permits in this table (Title 2, Chapter 3).
The municipality needs 8 weeks (standard procedure) to assess your application. Sometimes this takes 26 weeks (extended procedure), for example if you want to do something that is not in the zoning plan. The municipality can extend the period once by 6 weeks.
You may lodge an objection within 6 weeks after a permit has been granted. Proprties with monumantal status may not be demolished within those 6 weeks.