Applying for an environment and planning permit

Municipality Leidschendam-Voorburg: Applying for an environment and planning permit

Published by:
Municipality Leidschendam-Voorburg
Checked 25 Jan 2024
2 min read
Nederlandse versie

Go to the online service counter Omgevingsloket (in Dutch) to check if you need an environment and planning permit (omgevingsvergunning). In the Omgevingsloket you can see which rules apply in your municipality. You can then use the Omgevingsloket to apply online for an environment and planning permit or submit a notification.

all-in-one permit for physical aspects
  1. Go to Home - Omgevingsloket (overheid.nl) (the online environment service counter, in Dutch).
  2. Run a permit check to see if you need a permit or if you must submit a notification.
  3. If you need a permit, you can apply for it at once online on Omgevingsloket or send in a written application. Log in with DigiD (for individuals) or eHerkenning (for businesses).
  4. If you have to submit a notification, you can do so at once on Omgevingsloket. Log in with DigiD (for individeuals) or eHerkenning (for businesses).

The cost depends on which all-in-one permit for physical aspects you apply for. Note that you must pay even if your application is rejected.

The municipality has 8 weeks (short procedure) to assess your application. In some cases, the municipality will take up to 6 months (extended procedure) to assess your application. This may be the case if you want something different from what is stated in the environment plan (omgevingsplan). The municipality can extend the period once by a period of 6 weeks.

Do you want to object? In this case, the following rules apply.

  • For a standard all-in-one permit for physical aspects (8 weeks), you can file an objection within 6 weeks of the decision being published. How to do this is stated in the published decisions.
  • Does it concern an extended all-in-one permit for physical aspects (26 weeks)? Then it is issued a a draft decision. You can submit your opinion within 6 weeks. After that, a final decision will be made.. You can appeal to the district court within 6 weeks.

Good to know

You must not start work until you have obtained the permit. If you start before that, you may have to undo the work at your own expense.