Applying for an environment and planning permit

Municipality Maassluis: Applying for an environment and planning permit

Published by:
Municipality Maassluis
Checked 1 Feb 2023
2 min read
Nederlandse versie

Do you want to know if you have to submit a notification or if you need an all-in-one permit for physical aspects (omgevingsvergunning)? You can do an online permit check on the online service counter (omgevingsloket in Dutch).

The result of the permit check will show you which documents you must enclose. An architect or building contractor can help you with this.

  1. Go to Omgevingsloket online (the online environment service counter, in Dutch).
  2. Run a permit check to see if you need a permit or if you must submit a notification.
  3. If you need a permit, you can apply for it at once online on Omgevingsloket or send in a written application. Log in with DigiD (for individuals) or eHerkenning (for businesses).
  4. If you have to submit a notification, you can do so at once on Omgevingsloket. Log in with DigiD (for individeuals) or eHerkenning (for businesses).

The cost depends on which all-in-one permit for physical aspects you apply for. Note that you must pay even if your application is rejected.  For more information or queastions, please fill in a contact form by clicking on the following link : https://mijn.maassluis.nl/aanvragen/2867/onbekend/contact-form

The municipality needs 8 weeks (standard procedure) to assess your application. Sometimes this takes 26 weeks (extended procedure), for example if you want to do something that is not in the zoning plan. The municipality can extend the period once by 6 weeks.

You can view the list of permit applications and decisions hereZoeken in officiële bekendmakingen | Overheid.nl > Officiële bekendmakingen (officielebekendmakingen.nl).

Do you want to object? In this case, the following rules apply.

  • For a standard all-in-one permit for physical aspects (8 weeks), you can file an objection within 6 weeks of the decision being published. How to do this is stated in the published decisions.
  • Does it concern an extended all-in-one permit for physical aspects (26 weeks)? Then it is issued a a draft decision. You can submit your opinion within 6 weeks. After that, a final decision will be made.. You can appeal to the district court within 6 weeks. You can send your letter to: Recahtbank sector Bestuursrecht, postbus 50951, 3007 BM Rotterdam.

Good to know

You must not start work until you have obtained the permit. If you start before that, you may have to undo the work at your own expense.

This webpage is part of an EU quality network

Questions relating to this article?

Please contact theMunicipality Maassluis

+31105931931Visit the websiteContact form

Koningshoek 93050

3144BA Maassluis

Opening hours

Monday
8:00 - 16:00
Tuesday
8:00 - 16:00
Wednesday
8:00 - 16:00
Thursday
8:00 - 16:00
Friday
8:00 - 16:00
Saturday
Closed
Sunday
Closed