Check if you need an environment and planning permit and apply
Go to the online service counter Omgevingsloket (in Dutch) to check if you need an environment and planning permit (omgevingsvergunning). In the Omgevingsloket you can see which rules apply in your municipality. You can then use the Omgevingsloket to apply online for an environment and planning permit or submit a notification.
Do the permit check in the Omgevingsloket to see which documents you have to submit.
Environmental management notification
You must submit the environmental management notification online via the AIM (in Dutch).
All-in-one permit for physical aspects (environmental permit)
If you start, change, or expand a business, you must apply for an environmental permit from the Online environment portal:
1. Go to the online service counter Omgevingsloket online (in Dutch)2. Log in with DigiD (for individuals) or eHerkenning (for businesses).
Environmental management notification
A environmental management notification is free of charge.
All-in-one permit for physical aspects (environmental permit)
The costs depend on which permit you apply for. You must pay even if you do not get the permit. Please go to our page ‘Bouwen en Verbouwen’ for the costs.
The municipality will need 8 weeks (standard procedure) to assess your application. Sometimes it can take 26 weeks (extended procedure), for example if you want to deviate from the zoning plan. The municipality can extend the period once by 6 weeks.
You can view the list of permit applications and decisions at Officiëlebekendmakingen.nl.
If you want to object, the following applies.
- For a standard all-in-one permit for physical aspects (8 weeks), you must file an objection within 6 weeks after the decision is published. How to do this is stated in the published decision.
- Does it concern an extended all-in-one permit for physical aspects (26 weeks)? Then it is issued as a draft decision. You can submit your opinion within 6 weeks. After that, a final decision will be made. You can appeal to the district court within 6 weeks. In our decision you will read which district court.