Municipality Terneuzen: Environment and planning permit for environmentally harmful activities
Environmental management notification
Do you have a type B business? You must notify the municipality of your business activities. You do this by way of an environmental management notification via the Activities Decree online module Activities Decree online module (Activiteitenbesluit Internet Module, AIM, in Dutch).
You must submit the notification at least 4 weeks before starting, changing, or expanding your business.
All-in-one permit for physical aspects (environmental permit)
Do you have a type C business? You must apply for an all-in-one permit for physical aspects.
You must apply for the all-in-one permit for physical aspects at least 4 weeks before starting, changing, or expanding your business.
Apply for an environmental permitEnvironmental management notification and all-in-one permit for physical aspects (environmental permit)
If you start, change, or expand a business, you must apply for an environmental permit from the Online environment portal:
1. Go to the online service counter Omgevingsloket online (in Dutch)
2. Log in with DigiD (for individuals) or eHerkenning (for businesses).
Environmental management notification
A environmental management notification is free of charge.
All-in-one permit for physical aspects (environmental permit)
The costs depend on which permit you apply for. You must pay even if you do not get the permit.
Look for the costs on our website: https://www.terneuzen.nl/Inwoners_Terneuzen/Bouwen/Omgevingsvergunning_aanvragen
The municipality needs 8 weeks (standard procedure) to assess your application. The municipality can extend the period once by 6 weeks. Sometimes there isan extended procedure, for example if you want to do something that is not in the environmental plan.
You can view the list of permit applications and decisions here: https://www.terneuzen.nl/Onze_Organisatie/Actueel/Bekendmakingen
Do you want to object? In this case, the following rules apply.
- For a standard all-in-one permit for physical aspects (8 weeks), you can file an objection within 6 weeks of the decision being published. How to do this is stated in the published decisions.
- Does it concern an extended all-in-one permit for physical aspects? Then it is issued a a draft decision. You can submit your opinion within 6 weeks. After that, a final decision will be made.. You can appeal to the district court within 6 weeks.
Good to know
You must not start work until you have obtained the permit. If you start before that, you may have to undo the work at your own expense.